For a small, straightforward extension requiring planning permission, allow approximately 9–12 months from first meeting to completion. Larger or more involved projects take longer. A shorter programme is possible, but requires more intensive resourcing, which is reflected in the fee.

A typical small project, stage by stage

  1. Measured survey: 1–2 weeks. Ground investigations are best commissioned at the same stage, so that their findings inform the design.
  2. Concept design: 2–3 weeks. We model the existing house and the design options in 3D, so that each option can be clearly understood.
  3. Planning drawings: around 2 weeks once a concept is chosen.
  4. Planning application: 1–2 weeks for the council to validate the application, followed by a statutory determination period of 8 weeks.
  5. Technical design: at least 3–4 weeks for Building Regulations drawings, specification, structural integration, detailing and the schedule of works.
  6. Tender: 3–4 weeks for contractors to price, then 1–2 weeks to analyse the tenders and appoint a contractor.
  7. Construction: around 6 months for a small project, with the contract administered throughout.

The design stage is where timescales most often extend, and for good reason. Many clients discover a wider range of possibilities than they expected, and considering them properly takes time. We regard that time as well spent: changing a drawing early on costs very little, whereas changing a wall on site does not.

The consultants most projects need

We obtain quotations on our clients’ behalf and advise when each consultant should be appointed. Appointing too early risks paying for work that changes after planning; too late risks delay.

  • Ground investigation: recommended wherever new foundations are needed, and best commissioned alongside the measured survey.
  • Structural engineer: almost always required, usually appointed after planning, during technical design.
  • SAP energy assessor: almost always required, particularly with generous glazing, once the design is confirmed.
  • Building Control: always required, as technical drawings are prepared.
  • Build-over agreement: needed on around a third of our projects, where building over or within 3m of a public sewer. Apply as early as practical, as approvals take time.
  • Party wall surveyor: common on constrained sites, usually after planning, or earlier where the programme is tight.

The Party Wall Act

The Party Wall etc. Act 1996 applies in England and Wales where work affects a shared wall, where a new wall is built on or up to the boundary, or where foundations are excavated within 3m of a neighbouring structure and deeper than its foundations (or within 6m, in some circumstances).

Written notice must be served one month before excavation or a new boundary wall, and two months before work to an existing party wall. If the neighbour does not consent in writing within 14 days, surveyors are appointed to agree an award before work can begin. The building owner normally meets the surveyors’ fees. Where a project is close to a neighbouring property, party wall matters should be planned as soon as the design is settled.

Principal Designer and Principal Contractor

Since October 2023, the Building Regulations in England have required every project, including home extensions, to have a Principal Designer and a Principal Contractor, who plan, manage and monitor the design and the building work so that both comply. Where a homeowner makes no appointment, the designer in control of the design work takes the role by default, as does the contractor in control of the building work. Compliance declarations are required before Building Control can issue a completion certificate.

GAD acts as Principal Designer on the projects we design, so that the role is held by those who know the design best. More on the Principal Designer role.


If you would like a programme for your own project, get in touch.