On a new build, the Architect leads the design and coordinates a wider team of consultants from feasibility to completion. The principles are those of any project, but the scale brings additional responsibilities: more consultants to coordinate, planning conditions to discharge, and warranty requirements to meet. Warranty cover, from a provider such as NHBC, should be arranged before construction begins, as providers inspect the work at key stages and most mortgage lenders require it.

A new build also has advantages over an extension. There is no existing structure to connect to, and that junction between old and new is where many difficulties arise on refurbishment projects.

Procurement

  • Traditional. The design is completed, then tendered to contractors pricing the same information. This gives the greatest control over quality and scope, and like-for-like competitive pricing; construction begins once the design is complete.
  • Design and build. The contractor takes responsibility for design and construction. This gives earlier cost certainty and a single point of responsibility, often favoured by funders; quality depends on the detail of the Employer’s Requirements and the Architect’s continued involvement.

Traditional procurement is our standard route on projects of every size, as it gives the greatest control over quality and scope. Where a developer prefers design and build, the quality of the scheme rests on how thoroughly it is detailed before the contractor takes over, which plays to our strengths. We prepare comprehensive Employer’s Requirements, or are novated to the contractor to complete the design, so that the design intent is carried through.

Cost

New-build costs depend on the construction method, the specification and, above all, the site: whether piling is needed, how much earth must be moved, whether utilities exist, and what access and highway works are required. For that reason we avoid relying on a single headline rate.

We begin with area-based estimates at feasibility, then move to elemental cost modelling as the design develops, built up from the components of the building using current costs. Estimates are updated at key stages, so the cost effect of any significant change is clear. On larger schemes a quantity surveyor may be appointed. Where budget is under pressure, value engineering is a joint discussion with the client and engineers about which elements are essential and where compromise is acceptable.

The construction of new homes is generally zero-rated for VAT, unlike extensions, although professional fees are not. Specialist tax advice should be taken early.

Programme

Planning is usually the most significant hurdle. After validation, authorities aim to determine minor applications within 8 weeks and major applications within 13 weeks, and conditions within a further 8. Once consent is secured, technical design and the discharge of conditions run together: a couple of months for smaller or repetitive schemes, longer for larger or more varied ones. Builds can be phased to suit funding or sales.

As a broad indication, a scheme of two or three homes might take around 18–24 months from site appraisal to completion. Programmes most often slip on planning, seasonal ecology surveys, utility connections and pre-commencement conditions, so these are addressed from the outset.

Energy and the Future Homes Standard

The Future Homes Standard takes effect in England on 24 March 2027 for homes with a Building Regulations application after that date. In practice it makes heat pumps the expected heating solution for houses and requires on-site renewable electricity, usually solar panels. Homes with an earlier application must start construction before 24 March 2028 to remain under the previous standard. Schemes at feasibility stage now should be designed with it in mind.

Our approach is fabric first: an airtight, well-insulated envelope with thermal bridging designed out, so that heating demand is small and heating choices become simpler. An airtight home needs planned ventilation, typically mechanical ventilation with heat recovery, and new homes must be assessed for overheating under Part O, which shapes glazing, orientation and shading. We also consider how the fabric stores heat: thermal mass and insulation such as wood fibre help keep temperatures stable through the day and the seasons. Where clients’ aspirations allow, we favour natural, low-emission materials inside the home.

For developers, a useful principle is to commit early to what is hard to change later, such as insulation, airtightness and orientation, and to plan for what can be upgraded as technology and budgets allow, such as batteries or additional solar capacity.