Whether a site is viable depends on its planning context, its constraints and the client’s objectives. We test those through a feasibility study, which sets out what the site could accommodate, the key risks, and the areas and indicative costs needed for a financial appraisal.

Starting with the client’s objectives

Every site begins as an open canvas, shaped by its current use, its history and what stands on it today. Experienced developers usually arrive with a clear direction, informed by their own appraisals and knowledge of their market, and our role is to test it thoroughly. Clients developing for the first time may have a broader aim, typically new homes, and we help shape it into a viable proposal.

We assess the planning context (local policy, design guidance and planning history), the site’s constraints (neighbours, access, topography, trees, ecology, flood risk and contamination), and above all its scale. The number of homes is pivotal, as thresholds for affordable housing, contributions and levies change with the size of a scheme.

The feasibility study typically includes a site analysis and constraints plan, massing options showing unit numbers and mix, gross internal areas, and an indicative build cost. On smaller schemes we can support the financial appraisal directly.

Recent examples range from replacing a single house on an under-used plot with two or three new homes, to a substantial site proposed for 30–40 holiday accommodation units with hospitality and leisure facilities, which required extensive pre-application discussion, detailed site investigation and early engagement with the local community.

Choosing the planning route

The route depends on how certain the principle of development is.

  • Pre-application advice gives an informal, non-binding view from the planning authority. On larger schemes it is invaluable, shaping both the proposal and the choice of route.
  • Outline planning permission establishes the principle, with detailed matters reserved for later. It suits sites where resistance is possible, reducing risk before detailed design costs are committed.
  • Full planning permission suits straightforward schemes where the principle is clear, such as additional homes on an established residential plot.
  • Permission in principle is a two-stage route for housing schemes of fewer than 10 homes on sites under 1 hectare. The first stage considers only location, land use and amount of development, and should be decided within 5 weeks; Technical Details Consent follows.

Planning obligations and levies

Obligations form a key part of the appraisal, so we identify and cost them at feasibility stage, making prudent allowances that are refined as the design develops. Where a planning consultant is appointed, their advice is integrated throughout.

  • Community Infrastructure Levy (CIL): a fixed charge per square metre of new floorspace, where the authority has adopted it. The required forms, including a commencement notice, must be submitted before work starts, or reliefs can be lost and surcharges incurred.
  • Section 106 agreements: site-specific obligations such as affordable housing, highway works or open space.
  • Affordable housing: generally sought on major development of 10 or more homes, with the proportion set locally. The August 2026 National Planning Policy Framework also introduced a medium development category of 10 to 49 homes, so local and national policy should be checked on every site.
  • Biodiversity net gain: most development must deliver at least a 10% gain, secured for 30 years. For applications from 6 August 2026, sites of 0.2 hectares or less are exempt unless they affect priority habitat.
  • Building Safety Levy: since 1 October 2026, charged per square metre on most developments of 10 or more dwellings.
  • Habitat mitigation: across much of Essex, the Essex Coast RAMS tariff of £476 per net new dwelling applies from 1 August 2026, including some holiday accommodation.
  • Highways and drainage: new accesses, junction works and sustainable drainage all affect layout and external works costs.

Surveys to commission early

Most sites need a topographical survey, ecology, arboricultural, ground investigation, flood risk and drainage, transport, heritage and utilities assessments, and, where buildings are to be demolished, an asbestos survey. Some cannot wait: bat emergence surveys are restricted to May to September, and missing that window can delay an application by months. We coordinate surveys and consultants on our clients’ behalf, so that the planning application is complete and robust when submitted.


If you have a site in mind, a feasibility study is the most effective first step. Get in touch.